Skip to content

Commit eafd116

Browse files
g1-ghutzgitbook-bot
authored andcommitted
GITBOOK-951: Georgia's May 15 changes
1 parent 7b21a9e commit eafd116

File tree

9 files changed

+68
-15
lines changed

9 files changed

+68
-15
lines changed

SUMMARY.md

Lines changed: 7 additions & 1 deletion
Original file line numberDiff line numberDiff line change
@@ -168,7 +168,13 @@
168168
* [Delivery Assurance quarterly reports](intersect-operational-services/2025-delivery-assurance-contract-updates/delivery-assurance-quarterly-reports.md)
169169
* [Technical steering committee contracts](intersect-operational-services/2025-delivery-assurance-contract-updates/technical-steering-committee-contracts/README.md)
170170
* [Tweag - Ouroborus Peras protocol](intersect-operational-services/2025-delivery-assurance-contract-updates/technical-steering-committee-contracts/tweag-ouroborus-peras-protocol.md)
171-
* [Membership & Community committee contracts](intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts.md)
171+
* [Membership & Community committee contracts](intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/README.md)
172+
* [Japan Community Hub Interim Contract](intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/japan-community-hub-interim-contract.md)
173+
* [LATAM Community Hub Interim Contract](intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/latam-community-hub-interim-contract.md)
174+
* [Sri Lanka Community Hub Interim Contract](intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/sri-lanka-community-hub-interim-contract.md)
175+
* [Africa Community Hub Interim Contract](intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/africa-community-hub-interim-contract.md)
176+
* [North America Community Hub Interim Contract](intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/north-america-community-hub-interim-contract.md)
177+
* [Europe Community Hub Interim Contract](intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/europe-community-hub-interim-contract.md)
172178
* [Civics Committee](intersect-operational-services/2025-delivery-assurance-contract-updates/civics-committee.md)
173179
* [Product committee](intersect-operational-services/2025-delivery-assurance-contract-updates/product-committee/README.md)
174180
* [Dquadrant - GovTool Maintenance - Integrated Testing](intersect-operational-services/2025-delivery-assurance-contract-updates/product-committee/dquadrant-govtool-maintenance-integrated-testing.md)

intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts.md

Lines changed: 0 additions & 14 deletions
This file was deleted.

intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/README.md

Lines changed: 14 additions & 0 deletions
Original file line numberDiff line numberDiff line change
@@ -0,0 +1,14 @@
1+
---
2+
description: To be updated once contracts have been awarded.
3+
---
4+
5+
# Membership & Community committee contracts
6+
7+
This page covers everything related to the contracts that were proposed by the community to be contracted via the Membership & Community Committee. _Note that some of these contracts were established through the original 2024 contracting process, with funding provided by the CDH. Any contracts awarded from June 2025 onward will be financed through the Treasury withdrawal, in alignment with the budget process._
8+
9+
## **Contract overview section**
10+
11+
<table data-full-width="false"><thead><tr><th width="131">Supplier</th><th width="147">Contract</th><th>Contract Date</th><th>Contract Description</th><th>Contract Amount<select multiple><option value="1suRQbkRqH2z" label="Ongoing" color="blue"></option><option value="T4zEAlmGO1Vm" label="Complete" color="blue"></option></select></th><th width="160">Contract Amount</th></tr></thead><tbody><tr><td>Takatsuki Kyosuke</td><td><a href="japan-community-hub-interim-contract.md">Japan Community Hub Interim Contract</a></td><td>01/04/2025 - 30/06/2025</td><td>This SoW will enable the Japan community hub to continue<br>regional activities until the Treasury<br>withdrawal</td><td><span data-option="1suRQbkRqH2z">Ongoing</span></td><td>₫12</td></tr><tr><td>Mauro Andreoli</td><td><a href="latam-community-hub-interim-contract.md">LATAM Community Hub Interim Contract</a></td><td>01/04/2025 - 30/06/2025</td><td>This SoW will enable the LATAM community hub to continue<br>regional activities until the Treasury<br>withdrawal.</td><td><span data-option="1suRQbkRqH2z">Ongoing</span></td><td>₫23,438</td></tr><tr><td>CoinCeylon</td><td><a href="sri-lanka-community-hub-interim-contract.md">Sri Lanka Community Hub Interim Contract</a></td><td>01/04/2025 - 30/06/2025</td><td>This SoW will enable the Sri Lanka community hub to continue<br>regional activities until the Treasury<br>withdrawal</td><td><span data-option="1suRQbkRqH2z">Ongoing</span></td><td>₫18,182</td></tr><tr><td>WADA</td><td><a href="africa-community-hub-interim-contract.md">Africa Community Hub Interim Contract</a></td><td>01/04/2025 - 30/06/2025</td><td>This SoW will enable the Africa community hub to continue<br>regional activities until the Treasury<br>withdrawal.</td><td><span data-option="1suRQbkRqH2z">Ongoing</span></td><td>₫18,182</td></tr><tr><td>AWEN</td><td><a href="north-america-community-hub-interim-contract.md">North America Community Hub Interim Contract</a></td><td>01/04/2025 - 30/06/2025</td><td>This SoW will enable the North America community hub to continue<br>regional activities until the Treasury<br>withdrawal.</td><td><span data-option="1suRQbkRqH2z">Ongoing</span></td><td>₫16,216</td></tr><tr><td>Clay Nation</td><td><a href="europe-community-hub-interim-contract.md">Europe Community Hub Interim Contract</a></td><td>01/04/2025 - 30/06/2025</td><td>This SoW will enable the Europe community hub to continue<br>regional activities until the Treasury<br>withdrawal.</td><td><span data-option="1suRQbkRqH2z">Ongoing</span></td><td>₫15,385</td></tr></tbody></table>
12+
13+
## Overview of current Membership & Community committee milestones
14+

intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/africa-community-hub-interim-contract.md

Lines changed: 7 additions & 0 deletions
Original file line numberDiff line numberDiff line change
@@ -0,0 +1,7 @@
1+
# Africa Community Hub Interim Contract
2+
3+
* Supplier: WADA
4+
* Contract Name: Africa Community Hub Interim Contract
5+
* Contract Date: 01/04/2025 - 30/06/2025
6+
7+
<table data-full-width="true"><thead><tr><th width="152">Milestone</th><th width="158">Completion Date</th><th width="326">Milestone Description</th><th>Milestone Amount</th><th width="160">Milestone Status<select><option value="tuQZQU0qZdoU" label="Not Started" color="blue"></option><option value="egD9AGmh1U3S" label="On Track" color="blue"></option><option value="Re3cd2eP2WaH" label="Complete" color="blue"></option><option value="bEAnsa2nIuMk" label="Delayed" color="blue"></option></select></th><th width="165.77783203125">MAF</th></tr></thead><tbody><tr><td>Commencement Payment</td><td>04/04/25</td><td></td><td>7,576 ada</td><td><span data-option="Re3cd2eP2WaH">Complete</span></td><td>No MAF required</td></tr><tr><td>Month 1</td><td>01/05/2025</td><td>Monthly Town Hall<br>meeting, Social Media, Attend/host any<br>specified events, Host at least one X<br>Space, Update Status<br>Report in line with Hub Shaper’s Handbook &#x26; Update events<br>tracker in line with Hub Shaper’s Handbook</td><td>4,545 ada</td><td><span data-option="Re3cd2eP2WaH">Complete</span></td><td><a href="https://drive.google.com/file/d/1_QBVhPcEJFsKAQjYAahIH6qWXy5dSKBS/view?usp=drive_link">https://drive.google.com/file/d/1_QBVhPcEJFsKAQjYAahIH6qWXy5dSKBS/view?usp=drive_link</a></td></tr><tr><td>Month 2 </td><td></td><td>""</td><td>3030 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 3</td><td></td><td>""</td><td>3,030 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr></tbody></table>

intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/europe-community-hub-interim-contract.md

Lines changed: 7 additions & 0 deletions
Original file line numberDiff line numberDiff line change
@@ -0,0 +1,7 @@
1+
# Europe Community Hub Interim Contract
2+
3+
* Supplier: ClayNation
4+
* Contract Name: Europe Community Hub Interim Contract
5+
* Contract Date: 01/04/2025 - 30/06/2025
6+
7+
<table data-full-width="true"><thead><tr><th width="152">Milestone</th><th width="158">Completion Date</th><th width="326">Milestone Description</th><th>Milestone Amount</th><th width="160">Milestone Status<select><option value="tuQZQU0qZdoU" label="Not Started" color="blue"></option><option value="egD9AGmh1U3S" label="On Track" color="blue"></option><option value="Re3cd2eP2WaH" label="Complete" color="blue"></option><option value="bEAnsa2nIuMk" label="Delayed" color="blue"></option></select></th><th width="165.77783203125">MAF</th></tr></thead><tbody><tr><td>Commencement Payment</td><td>07/04/25</td><td></td><td>6,154 ada</td><td><span data-option="Re3cd2eP2WaH">Complete</span></td><td>No MAF required</td></tr><tr><td>Month 1</td><td></td><td>Monthly Town Hall<br>meeting, Social Media, Attend/host any<br>specified events, Host at least one X<br>Space, Update Status<br>Report in line with Hub Shaper’s Handbook &#x26; Update events<br>tracker in line with Hub Shaper’s Handbook</td><td>3,077 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 2 </td><td></td><td>""</td><td>3,077 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 3</td><td></td><td>""</td><td>3,077 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr></tbody></table>

intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/japan-community-hub-interim-contract.md

Lines changed: 10 additions & 0 deletions
Original file line numberDiff line numberDiff line change
@@ -0,0 +1,10 @@
1+
# Japan Community Hub Interim Contract
2+
3+
* Supplier: Takatsuki Kyosuke
4+
* Contract Name: Japan Community Hub Interim Contract
5+
* Contract Date: 01/04/2025 - 30/06/2025
6+
7+
### Contract Details
8+
9+
<table data-full-width="true"><thead><tr><th width="154">Milestone</th><th width="147">Completion Date</th><th width="326">Milestone Description</th><th>Milestone Amount</th><th width="160">Milestone Status<select><option value="tuQZQU0qZdoU" label="Not Started" color="blue"></option><option value="egD9AGmh1U3S" label="On Track" color="blue"></option><option value="Re3cd2eP2WaH" label="Complete" color="blue"></option><option value="bEAnsa2nIuMk" label="Delayed" color="blue"></option></select></th><th width="165.77783203125">MAF</th></tr></thead><tbody><tr><td>Commencement Payment</td><td></td><td></td><td>6 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 1</td><td></td><td>Monthly Town Hall<br>meeting, Social Media, Attend/host any<br>specified events, Host at least one X<br>Space, Update Status<br>Report in line with Hub Shaper’s Handbook &#x26; Update events<br>tracker in line with Hub Shaper’s Handbook</td><td>2 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 2 </td><td></td><td>""</td><td>2 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 3</td><td></td><td>""</td><td>1 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr></tbody></table>
10+

intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/latam-community-hub-interim-contract.md

Lines changed: 9 additions & 0 deletions
Original file line numberDiff line numberDiff line change
@@ -0,0 +1,9 @@
1+
# LATAM Community Hub Interim Contract
2+
3+
* Supplier: Mauro Andreoli
4+
* Contract Name: LATAM Community Hub Interim Contract
5+
* Contract Date: 01/04/2025 - 30/06/2025
6+
7+
### Contract Details
8+
9+
<table data-full-width="true"><thead><tr><th width="152">Milestone</th><th width="158">Completion Date</th><th width="326">Milestone Description</th><th>Milestone Amount</th><th width="160">Milestone Status<select><option value="tuQZQU0qZdoU" label="Not Started" color="blue"></option><option value="egD9AGmh1U3S" label="On Track" color="blue"></option><option value="Re3cd2eP2WaH" label="Complete" color="blue"></option><option value="bEAnsa2nIuMk" label="Delayed" color="blue"></option></select></th><th width="165.77783203125">MAF</th></tr></thead><tbody><tr><td>Commencement Payment</td><td>08/04/25</td><td></td><td>9,375 ADA</td><td><span data-option="Re3cd2eP2WaH">Complete</span></td><td>No MAF required</td></tr><tr><td>Month 1</td><td></td><td>Monthly Town Hall<br>meeting, Social Media, Attend/host any<br>specified events, Host at least one X<br>Space, Update Status<br>Report in line with Hub Shaper’s Handbook &#x26; Update events<br>tracker in line with Hub Shaper’s Handbook</td><td>4,688 ADA</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 2 </td><td></td><td>""</td><td>4,688 ADA</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 3</td><td></td><td>""</td><td>4,688 ADA</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr></tbody></table>

intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/north-america-community-hub-interim-contract.md

Lines changed: 7 additions & 0 deletions
Original file line numberDiff line numberDiff line change
@@ -0,0 +1,7 @@
1+
# North America Community Hub Interim Contract
2+
3+
* Supplier: Awen
4+
* Contract Name: North America Community Hub Interim Contract
5+
* Contract Date: 01/04/2025 - 30/06/2025
6+
7+
<table data-full-width="true"><thead><tr><th width="152">Milestone</th><th width="158">Completion Date</th><th width="326">Milestone Description</th><th>Milestone Amount</th><th width="160">Milestone Status<select><option value="tuQZQU0qZdoU" label="Not Started" color="blue"></option><option value="egD9AGmh1U3S" label="On Track" color="blue"></option><option value="Re3cd2eP2WaH" label="Complete" color="blue"></option><option value="bEAnsa2nIuMk" label="Delayed" color="blue"></option></select></th><th width="165.77783203125">MAF</th></tr></thead><tbody><tr><td>Commencement Payment</td><td>01/04/25</td><td></td><td>8,108 ada</td><td><span data-option="Re3cd2eP2WaH">Complete</span></td><td>No MAF required</td></tr><tr><td>Month 1</td><td>03/05/25</td><td>Monthly Town Hall<br>meeting, Social Media, Attend/host any<br>specified events, Host at least one X<br>Space, Update Status<br>Report in line with Hub Shaper’s Handbook &#x26; Update events<br>tracker in line with Hub Shaper’s Handbook</td><td>2,703 ada</td><td><span data-option="Re3cd2eP2WaH">Complete</span></td><td><a href="https://drive.google.com/file/d/1Cy60db2fdhPn27nVLYFCbwypPL0MxtIa/view?usp=drive_link">https://drive.google.com/file/d/1Cy60db2fdhPn27nVLYFCbwypPL0MxtIa/view?usp=drive_link</a></td></tr><tr><td>Month 2 </td><td></td><td>""</td><td>2,703 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 3</td><td></td><td>""</td><td>2,703 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr></tbody></table>

intersect-operational-services/2025-delivery-assurance-contract-updates/membership-and-community-committee-contracts/sri-lanka-community-hub-interim-contract.md

Lines changed: 7 additions & 0 deletions
Original file line numberDiff line numberDiff line change
@@ -0,0 +1,7 @@
1+
# Sri Lanka Community Hub Interim Contract
2+
3+
* Supplier: CoinCeylon
4+
* Contract Name: Sri Lanka Community Hub Interim Contract
5+
* Contract Date: 01/04/2025 - 30/06/2025
6+
7+
<table data-full-width="true"><thead><tr><th width="152">Milestone</th><th width="158">Completion Date</th><th width="326">Milestone Description</th><th>Milestone Amount</th><th width="160">Milestone Status<select><option value="tuQZQU0qZdoU" label="Not Started" color="blue"></option><option value="egD9AGmh1U3S" label="On Track" color="blue"></option><option value="Re3cd2eP2WaH" label="Complete" color="blue"></option><option value="bEAnsa2nIuMk" label="Delayed" color="blue"></option></select></th><th width="165.77783203125">MAF</th></tr></thead><tbody><tr><td>Commencement Payment</td><td>08/04/25</td><td></td><td>9,091 ada</td><td><span data-option="Re3cd2eP2WaH">Complete</span></td><td>No MAF required</td></tr><tr><td>Month 1</td><td>12/05/2025</td><td>Monthly Town Hall<br>meeting, Social Media, Attend/host any<br>specified events, Host at least one X<br>Space, Update Status<br>Report in line with Hub Shaper’s Handbook &#x26; Update events<br>tracker in line with Hub Shaper’s Handbook</td><td>3,030 ada</td><td><span data-option="Re3cd2eP2WaH">Complete</span></td><td><a href="https://drive.google.com/file/d/1OxtJLzt5gShZZ1XYPGaOL3imUrwKueri/view?usp=drive_link">https://drive.google.com/file/d/1OxtJLzt5gShZZ1XYPGaOL3imUrwKueri/view?usp=drive_link</a></td></tr><tr><td>Month 2 </td><td></td><td>""</td><td>3,030 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr><tr><td>Month 3</td><td></td><td>""</td><td>3,030 ada</td><td><span data-option="tuQZQU0qZdoU">Not Started</span></td><td></td></tr></tbody></table>

0 commit comments

Comments
 (0)