Skip to content

Commit d12ed87

Browse files
committed
Merged main into live
2 parents f6da725 + 6b97c09 commit d12ed87

File tree

1 file changed

+12
-11
lines changed

1 file changed

+12
-11
lines changed

docs/report/dashboards/team-velocity.md

Lines changed: 12 additions & 11 deletions
Original file line numberDiff line numberDiff line change
@@ -9,12 +9,12 @@ ms.topic: tutorial
99
ms.author: chcomley
1010
author: chcomley
1111
monikerRange: "<=azure-devops"
12-
ms.date: 03/12/2025
12+
ms.date: 07/02/2025
1313
---
1414

1515
# View and configure team velocity
1616

17-
[!INCLUDE [version-gt-eq-2019](../../includes/version-gt-eq-2019.md)]
17+
[!INCLUDE [version-lt-eq-azure-devops](../../includes/version-lt-eq-azure-devops.md)]
1818

1919
Velocity metrics provide valuable insights that help teams plan and [forecast](../../boards/sprints/forecast.md) sprints, and evaluate how accurately they estimate and meet planned commitments. These metrics indicate how much work a team can complete during a sprint, based on either **the count of work items completed** or **the sum of estimates** for effort (product backlog items), story points (user stories), or size (requirements). Use velocity to aid in determining team capacity, but don't confuse it with key performance indicators.
2020

@@ -23,11 +23,18 @@ Velocity metrics provide valuable insights that help teams plan and [forecast](.
2323
[!INCLUDE [temp](../includes/analytics-widgets-prerequisites.md)]
2424

2525
> [!TIP]
26-
> The images in this article might differ from what you see in your web portal. These differences can be due to updates to your web app, options enabled by you or your admin, and the process chosen when creating your project (Agile, Basic, Scrum, or CMMI). The Basic process is available starting from Azure DevOps Server 2019 Update 1.
26+
> The images in this article might differ from what you see in your web portal. These differences can be due to updates to your web app, options enabled by you or your admin, and the process chosen when creating your project (Agile, Basic, Scrum, or CMMI).
2727
28-
## Velocity chart types
28+
## Understand velocity numbers
29+
30+
**Velocity** represents the amount of work your team completed in past sprints, which helps predict future capacity:
31+
32+
- **When tracking by count**: Velocity shows the number of work items (user stories, bugs, tasks) completed per sprint
33+
- **When tracking by sum**: Velocity shows the total story points, effort hours, or size estimates completed per sprint
34+
35+
For example, if your team completed user stories worth 25 story points in Sprint 1, 30 story points in Sprint 2, and 28 story points in Sprint 3, your average velocity is approximately 28 story points per sprint. This average helps you plan how much work to commit to in future sprints.
2936

30-
::: moniker range=">= azure-devops-2020"
37+
## Velocity chart types
3138

3239
You can choose between two Velocity charts: the in-context Velocity chart from the Backlogs page and the Velocity widget for dashboards. Both charts help you quickly understand the workflow state categories described in the following table.
3340

@@ -61,15 +68,11 @@ You can configure each chart in the following ways:
6168
- Number of iterations.
6269

6370
The widget offers more configuration options. For more information, see [Configure and view Velocity charts](team-velocity.md).
64-
65-
::: moniker-end
6671

6772
<a id="velocity-chart"></a>
6873

6974
## View the Velocity in-context report
7075

71-
::: moniker range=">= azure-devops-2020"
72-
7376
Velocity reports are available for both product and portfolio backlogs. Each report includes interactive controls, allowing users to customize the view to their specific interests.
7477

7578
1. Sign in to your project (```https://dev.azure.com/{Your_Organization/Your_Project}```).
@@ -97,8 +100,6 @@ Velocity reports are available for both product and portfolio backlogs. Each rep
97100

98101
7. To return to the Analytics summary, select the :::image type="icon" source="../../media/icons/back-arrow.png" border="false"::: back arrow.
99102

100-
::: moniker-end
101-
102103
## Configure the Velocity widget
103104

104105
You can only configure your Velocity widget for a single team. If you want to view the velocity for several teams, then you must configure a portfolio management team that rolls up from several teams. For more information, see [Add teams](../../organizations/settings/add-teams.md).