+- The number of databases you can migrate to a SQL server Azure Virtual Machine depends on the hardware specification and workload, but there is no enforced limit. However, every migration operation (start migration, cutover) for each database will take few mins sequentially. For example, to migrate 100 databases, it may take approx. 200 (2 x 100) minutes to create the migration queue/s and approx. 100 (1 x 100) minutes to cutover all 100 databases (excluding backup and restore timing). Therefore, the migration will become slower as the number of databases increases. Microsoft advises either scheduling a longer migration window in advance based on rigorous migration testing or partitioning large number of databases into batches when migrating them to a SQL server Azure VM.