@@ -65,7 +65,7 @@ This device is shipped in a single box. Complete the following steps to unpack y
6565
1. Place the box on a flat, level surface.
6666
2. Inspect the box and the packaging foam for crushes, cuts, water damage, or any other obvious damage. If the box or packaging is severely damaged, don't open it. Contact Microsoft Support to help you assess whether the device is in good working order.
6767
3. Unpack the box. After unpacking the box, make sure that you have:
68-
- One single enclosure Edge device
68+
- One single enclosure Data Box Edge device
6969
- Two power cords
7070
- One rail kit assembly
7171
- A Safety, Environmental, and Regulatory Information booklet
@@ -95,7 +95,7 @@ Locate the components for installing the rail kit assembly:
9595
1. Two A7 Dell ReadyRails II sliding rail assemblies
9696
2. Two hook and loop straps
9797

98-
![Identify rail kit contents](./media/data-box-edge-deploy-install/identify-rail-kit-contents.png)
98+
![Identify rail kit contents](./media/data-box-edge-deploy-install/identify-rail-kit-contents.png)
9999

100100
### Install and remove tool-less rails (Square hole or round hole racks)
101101

@@ -107,7 +107,7 @@ Locate the components for installing the rail kit assembly:
107107
3. Engage the back end of the rail until it fully seats on the vertical rack flange and the latch clicks into place. Repeat these steps to position and seat the front end piece on the vertical rack flange.
108108
4. To remove the rails, pull the latch release button on the end piece midpoint and unseat each rail.
109109

110-
![Install and remove tool-less rails](./media/data-box-edge-deploy-install/installing-removing-tool-less-rails.png)
110+
![Install and remove tool-less rails](./media/data-box-edge-deploy-install/installing-removing-tool-less-rails.png)
111111

112112
### Install and remove tooled rails (Threaded hole racks)
113113

@@ -119,7 +119,7 @@ Locate the components for installing the rail kit assembly:
119119
3. Attach the left and right mounting rails to the front vertical rack flanges using two pairs of screws.
120120
4. Slide the left and right back brackets forward against the rear vertical rack flanges and attach them using two pairs of screws.
121121

122-
![Install and remove tooled rails](./media/data-box-edge-deploy-install/installing-removing-tooled-rails.png)
122+
![Install and remove tooled rails](./media/data-box-edge-deploy-install/installing-removing-tooled-rails.png)
123123

124124
### Install the system in a rack
125125

@@ -128,15 +128,15 @@ Locate the components for installing the rail kit assembly:
128128
3. Push the system inward until the lock levers click into place.
129129
4. Press the slide-release lock buttons on both rails and slide the system into the rack.
130130

131-
![Install system in a rack](./media/data-box-edge-deploy-install/installing-system-rack.png)
131+
![Install system in a rack](./media/data-box-edge-deploy-install/installing-system-rack.png)
132132

133133
### Remove the system from the rack
134134

135135
1. Locate the lock levers on the sides of the inner rails.
136136
2. Unlock each lever by rotating it up to its release position.
137137
3. Grasp the sides of the system firmly and pull it forward until the rail standoffs are at the front of the J-slots. Lift the system up and away from the rack and place it on a level surface.
138138

139-
![Remove system from the rack](./media/data-box-edge-deploy-install/removing-system-rack.png)
139+
![Remove system from the rack](./media/data-box-edge-deploy-install/removing-system-rack.png)
140140

141141
### Engage and release the slam latch
142142

@@ -147,7 +147,7 @@ Locate the components for installing the rail kit assembly:
147147
2. The latches engage automatically as the system is pushed into the rack and are released by pulling up on the latches.
148148
3. To secure the system for shipment in the rack or for other unstable environments, locate the hard-mount screw under each latch and tighten each screw with a #2 Phillips screwdriver.
149149

150-
![Engage and release slam latch](./media/data-box-edge-deploy-install/engaging-releasing-slam-latch.png)
150+
![Engage and release slam latch](./media/data-box-edge-deploy-install/engaging-releasing-slam-latch.png)
151151

152152
### Route the cables
153153

@@ -159,15 +159,15 @@ Locate the components for installing the rail kit assembly:
159159
3. Thread the hook and loop straps through the slots on the outer CMA brackets on each side of the system to secure the cable bundles.
160160

161161

162-
![Route the cables](./media/data-box-edge-deploy-install/routing-cables.png)
162+
![Route the cables](./media/data-box-edge-deploy-install/routing-cables.png)
163163

164164
## Cable the device
165165

166-
The following procedures explain how to cable your Edge device for power and network.
166+
The following procedures explain how to cable your Data Box Edge device for power and network.
167167

168168
Before you start cabling your device, you need the following:
169169

170-
- Your Edge physical device, unpacked, and rack mounted.
170+
- Your Data Box Edge physical device, unpacked, and rack mounted.
171171
- Two power cables.
172172
- At least one 1-GbE RJ-45 network cable to connect to the management interface. There are two 1-GbE network interfaces, one management and one data, on the device.
173173
- One 25-GbE SFP+ copper cable for each data network interface to be configured. At least one data network interface from among PORT 2, PORT 3, PORT 4, PORT 5, or PORT 6 needs to be connected to the Internet (with connectivity to Azure).
@@ -176,7 +176,7 @@ Before you start cabling your device, you need the following:
176176
> [!NOTE]
177177
> - If you are connecting only one data network interface, we recommend that you use a 25/10-GbE network interface such as PORT 3, PORT 4, PORT 5, or PORT 6 to send data to Azure.
178178
> - For best performance and to handle large volumes of data, consider connecting all the data ports.
179-
> - The Edge device should be connected to the datacenter network so that it can ingest data from data source servers.
179+
> - The Data Box Edge device should be connected to the datacenter network so that it can ingest data from data source servers.
180180
181181
On your Data Box Edge device:
182182

@@ -230,5 +230,3 @@ Advance to the next tutorial to learn how to connect, set up, and activate your
230230

231231
> [!div class="nextstepaction"]
232232
> [Connect and set up Data Box Edge](./data-box-edge-deploy-connect-setup-activate.md)
233-
234-