Update scheduled-events.md
Added an explanatory sentence regarding minimum notice time of event scheduling. I supposed it was some difficult to understand what is the minimum notice time of event scheduling.
1 parent fac27d7 commit f0a4efa

File tree

1 file changed

+1
-1
lines changed

1 file changed

+1
-1
lines changed

articles/virtual-machines/windows/scheduled-events.md

Lines changed: 1 addition & 1 deletion
Original file line numberDiff line numberDiff line change
@@ -177,7 +177,7 @@ Each event is scheduled a minimum amount of time in the future based on the even
177177
| Redeploy | 10 minutes |
178178
| Terminate | [User Configurable](../../virtual-machine-scale-sets/virtual-machine-scale-sets-terminate-notification.md#enable-terminate-notifications): 5 to 15 minutes |
179179

180-
Once an event is scheduled, it will move into the `Started` state after it's been approved or the `NotBefore` time passes. However, in rare cases, the operation will be cancelled by Azure before it starts. In that case the event will be removed from the Events array, and the impact will not occur as previously scheduled.
180+
This means that you can detect a future schedule of event at least by the minimum notice time before the event occurs. Once an event is scheduled, it will move into the `Started` state after it's been approved or the `NotBefore` time passes. However, in rare cases, the operation will be cancelled by Azure before it starts. In that case the event will be removed from the Events array, and the impact will not occur as previously scheduled.
181181

182182
> [!NOTE]
183183
> In some cases, Azure is able to predict host failure due to degraded hardware and will attempt to mitigate disruption to your service by scheduling a migration. Affected virtual machines will receive a scheduled event with a `NotBefore` that is typically a few days in the future. The actual time varies depending on the predicted failure risk assessment. Azure tries to give 7 days' advance notice when possible, but the actual time varies and might be smaller if the prediction is that there's a high chance of the hardware failing imminently. To minimize risk to your service in case the hardware fails before the system-initiated migration, we recommend that you self-redeploy your virtual machine as soon as possible.