As we were adding framework agreement fields to the XML we ran into couple of problems:
"For any Result Notice without Group Framework Maximum Value (BT-156), and for which all Framework Maximum Value (BT-709) share a same currency, the Notice Framework Maximum Value (BT-118) value must be equal to the sum of Framework Maximum Value (BT-709) or to the sum of Framework Estimated Value (BT-660)" Why did we get this error if we don't have anything related to BT-709 or BT-660 in XML?
|
Beta Was this translation helpful? Give feedback.
Replies: 1 comment
-
Indeed, in later versions there will also be an error as BT-118 is about Framework Agreement and in absence of Framework Agreements, this information should not exist. In a later version (most likely SDK 1.8) a condition will be applied to prevent the specification of BT-118 when no awarded lot with a Framework Agreement exist. |
Beta Was this translation helpful? Give feedback.
Indeed, in later versions there will also be an error as BT-118 is about Framework Agreement and in absence of Framework Agreements, this information should not exist. In a later version (most likely SDK 1.8) a condition will be applied to prevent the specification of BT-118 when no awarded lot with a Framework Agreement exist.
BT-161 is about "execution" contracts (i.e. engaged amounts) and having Framework Agreements in a notice does not prevent the existence of "execution" contracts (a notice may cover various situations with some lot results being about execution contracts, inside or not a Framework contract, and others about framework contracts), so yes BT-161 is also allowed when th…