Course Matrix

Iteration 04

  • Start date: 03/21/2025
  • End date: 04/04/2025

1. Process

1.1 Roles & Responsibilities

Epic 1: Scheduler

Team Members: Austin, Minh, and Thomas

  • Develop a calendar interface that allows users to favourite their calendars.
  • Develop an interface that allows users to share their calendars with one another.
  • Develop an algorithm that allows users to compare two different timetables together.

Epic 2: AI Assistant

Team Members: Kevin

  • Develop an AI-powered chat interface that can create, delete, and show user timetables.

  • Refine AI-powered chat interface so that querying for database information is more reliable and understandable

  • Note taking & Documentation: Minh, Masahisa, and Thomas

    • Taking notes during stand-ups
    • Create sprint 4 documentation: iteration-plan-04, RPM, and sprint-04 review
    • Update System Design Document

In addition to their specific roles, all team members have a collective responsibility to support and assist other team members to ensure that the goals (listed in section 2.1) are achieved and develop a working prototype.

Epic 3: Deployment

Team Members: Masahisa

  • Create a dockerfile such that our application can be run on a docker image with application setup being done automatically.
  • Ensure that our application’s docker image runs on a VM instance accessible on the web.
  • Ensure that our deployed project automatically redeploys when a new version of our application is pushed that passes all unit testing.
  • Ensure that our application images are stored on dockerhub with a version tag and a master branch holding the latest version.

Epic 4: Unit Testing

Team Members: Austin, Minh, Thomas, Kevin

  • Create unit tests for our application functions (timetable, ai assistant, user stories, etc.) such that their functionality is clear and bug free.

1.2 Events

  • Initial planning meeting:

    • Location: Virtual
    • Time: 3/22/2025
    • Purposes:
      • Go over the sprint 4 requirements
      • Define tasks and responsibilities for each team member
  • Stand up meeting:

    • Location: Online or in-person depending on members availability
    • Time: Every Tuesday from 12 pm to 1 pm, Thursday and Sunday from 9 pm to 10 pm
    • Purposes
      • Progress updates: What has each member done since the last stand-up
      • Determine the next steps and deadlines
      • Discuss current blockers and possible solutions
  • Final review meeting

    • Location: Online
    • Time: 4/04/2025
    • Purposes:
      • Review features and deliverables implemented in sprint 4
      • Determine changes that need to be made in sprint 4

1.3 Artifacts

  • Our team will track the progress through Jira

    • Each user story will be uploaded to Jira as a ticket:

      • Categorized in the backlog by its epic, and execution sprint

      JIRA Backlog

      • Ticket details include: estimated story point to determine its priority, assignees

      Ticket Detail

      • Tickets of large user stories will be broken down into smaller child issues

      Ticket Description and Child Issue

      • Each ticket will also show:

        • Other tickets blocked by it

        Blocked tickets

        • Other tickets blocking it

        Blocking tickets

    • Additional tasks required during the development process will also be submitted as a task ticket on JIRA for tracking.

    • Students or groups of students will be assigned first to epic and then to the specific user story.

    • Workflow

    Ticket Workflow

  • Furthermore, we will implement a Burndown Chart, which will be included as burndown.pdf by the end of the sprint. This chart will also feature comments on the sprint's progress and a velocity comparison.

  • Below is an example Burndown Chart from Sprint 0:

Burndown Chart

2. Product

2.1 Goal and Tasks

1. Develop product features for the product demo:

  • Epic 1: Scheduler

  • Epic 2: AI Assistant

    • Delete confirmation for chatbot: SCRUM-148
    • Prevent Chatbot from creating more than 1 timetable at once: SCRUM-149
  • Epic 3: CI/CD Pipeline

3. Create sprint 4 documentation: SCRUM-176

2.2 Artifacts

Pages/Features

Scheduler

  • Option to favourite timetables for quick access.
  • Option to share/export timetable to other users
  • Option to compare two separate timetables
  • Enhance frontend UI to be more usable

AI Assistant

  • Ability to generate, delete, create, view timetables and more using AI chatbot
  • Deleting anything with chatbot must only be done after another user confirmation