utf8proj Quick Reference Card

DSL Syntax (.proj files)

Project

project "Name" {
    start: 2025-02-01
    end: 2025-06-30
    currency: EUR
}

Calendar

calendar "standard" {
    working_hours: 09:00-12:00, 13:00-17:00
    working_days: mon-fri
    holiday "Easter" 2025-04-18..2025-04-21
}

Resource

resource dev "Developer" {
    rate: 850/day
    capacity: 1.0
    efficiency: 1.0
}

Task

task impl "Implementation" {
    effort: 10d           # Person-time
    duration: 5d          # Calendar time (overrides effort)
    assign: dev, qa       # Resources
    depends: design       # Dependencies
    priority: 700         # Higher = first
    milestone: true       # Zero duration
}

Nested Tasks (WBS)

task phase1 "Phase 1" {
    task design "Design" { effort: 5d }
    task impl "Implement" { effort: 10d, depends: design }
}

Duration Units

Unit Meaning Example
h Hours 8h
d Days (8h) 5d
w Weeks (5d) 2w
m Months (20d) 3m

Dependencies

Syntax Type Meaning
depends: a FS Start after A finishes
depends: a SS SS Start when A starts
depends: a FF FF Finish when A finishes
depends: a SF SF Finish when A starts
depends: a + 2d Lag Wait 2 days after A
depends: a - 3d Lead Start 3 days before A ends
depends: a.50% Partial Start when A is 50% done

Constraints

must_start_on: 2025-03-01
must_finish_on: 2025-03-15
start_no_earlier_than: 2025-02-15
start_no_later_than: 2025-02-28
finish_no_earlier_than: 2025-03-10
finish_no_later_than: 2025-03-31

CLI Commands

# Schedule
utf8proj schedule project.proj -o schedule.json

# Render
utf8proj render project.proj --format svg -o timeline.svg
utf8proj render project.proj --format mermaid -o timeline.mmd

# What-if
utf8proj what-if project.proj --constraint "resource.dev.capacity = 0.5"

# Validate
utf8proj validate project.proj

# MS Project
utf8proj import project.xml -o project.proj
utf8proj export project.proj --format mspdi -o project.xml

Feature Flags

cargo build                          # heuristic only
cargo build --features bdd           # + BDD solver
cargo build --features sat           # + SAT solver
cargo build --features lua           # + Lua scripting
cargo build --features tjp           # + TaskJuggler compat
cargo build --features full          # all features

Key Formulas

Effort-based duration:

duration = effort / (∑ resource_capacity × resource_units × efficiency)

Slack/Float:

slack = late_start - early_start = late_finish - early_finish

Critical path: Tasks where slack = 0


Report Types

report gantt "timeline.svg" {
    tasks: all
    resources: show
    critical_path: highlight
}

report table "tasks.md" {
    type: tasks
    columns: id, name, start, finish, duration
}

report costs "budget.md" {
    type: costs
    columns: task, resource, effort, cost
}

Scheduling Tiers

Tier Algorithm Use Case Feature
1 Heuristic 95% of projects default
2 BDD What-if analysis bdd
3 SAT Complex constraints sat

Priority Rules

Rule Strategy
LongestPath Critical path first
MostSuccessors Most dependents first
ShortestDuration Quick wins first
HighestPriority User-defined
EarliestDeadline Constrained first

utf8dok Integration

[[fig-timeline]]
.Project Schedule
[schedule, report=gantt]
----
include::project.proj[]
----

License

MIT OR Apache-2.0 (your choice)