utf8proj Roadmap

Last Updated: 2026-01-30 Current Version: 0.16.0


Completed Features

All original v1.0 roadmap items have been implemented:

Feature Status Notes
Interactive Gantt Chart (HTML/SVG) Done Zoom, tooltips, dependency arrows, dark theme, now line
WASM Playground Done https://alanbld.github.io/utf8proj/
Resource Leveling Done RFC-0003, RFC-0014 (hybrid BDD)
Progress-Aware Scheduling Done RFC-0008, complete%, remaining duration
Baseline Management Done RFC-0013: save, list, compare
Excel Export Done RFC-0018: progress tracking, visual formatting
Now Line Rendering Done RFC-0017: status date marker on Gantt
Multiple Render Formats Done HTML, SVG, MermaidJS, PlantUML, Excel
Focus View Done RFC-0006: pattern-based filtering
LSP Support Done Diagnostics, hover, go-to-definition
Project Status Dashboard Done RFC-0019: text/JSON output, WASM, Excel sheet

Next Steps (Prioritized)

1. CLI Progress Update

Command: utf8proj progress --task=api_impl --complete=75

Why This Matters:

  • Update task progress without editing .proj files
  • Batch updates via CSV import
  • Integrates with CI/CD pipelines

Examples:

# Single task update
utf8proj progress project.proj --task=backend_api --complete=75

# With actual dates
utf8proj progress project.proj --task=frontend --complete=100 \
    --actual-start=2026-01-15 --actual-finish=2026-01-28

# Batch import
utf8proj progress project.proj --import=weekly_status.csv

Complexity: Medium (requires file modification logic) Impact: High (reduces manual editing errors)


2. Extended Task Status

Current: complete: 75%

Proposed:

task api_impl "API Implementation" {
    duration: 10d
    status: blocked          # or: on_hold, at_risk, cancelled
    status_reason: "Waiting for security review"
    status_since: 2026-01-25
}

Status Types:

  • not_started (default)
  • in_progress (has actual_start, no actual_finish)
  • complete (100% or has actual_finish)
  • blocked { reason, since } - External dependency
  • on_hold { reason } - Paused intentionally
  • at_risk { reason } - May miss deadline
  • cancelled { reason } - Removed from scope

Complexity: Medium (parser + domain model changes) Impact: Medium (better project visibility)


3. Schedule Playback

Command: utf8proj playback project.proj -o evolution.html

Why This Matters:

  • Visualize how the schedule evolved over time
  • Answer "What changed since last week?"
  • Stakeholder communication tool

Features:

  • Timeline slider showing schedule at each baseline
  • Highlight changes: tasks added/removed/delayed
  • Impact metrics: duration change, critical path shifts

Complexity: High (requires multiple baselines, animation) Impact: Medium (retrospectives, stakeholder reports)


4. Forecast Report

Command: utf8proj forecast project.proj --baseline=original

Output:

Forecast Report (vs baseline: original)
═══════════════════════════════════════

Projected Completion: 2026-05-15 (was 2026-04-30)
Schedule Variance:    +15 days
Cost Variance:        +€12,500

Top Delays:
  1. backend_api: +8 days (resource conflict)
  2. security_review: +5 days (external dependency)
  3. testing: +2 days (scope increase)

Recommendations:
  • Add resource to backend_api to recover 4 days
  • Escalate security_review with vendor

Complexity: Medium (builds on existing baseline compare) Impact: High (proactive risk management)


Post-v1.0 Features (Deferred)

Feature Notes
VS Code Extension Syntax highlighting, diagnostics, preview
GitHub Action CI/CD integration for schedule validation
EVM (Earned Value) CPI, SPI, EAC, VAC metrics
Plugin System Custom renderers, importers
Web UI Browser-based editing with collaboration
AI Forecasting ML-based completion predictions

Recommendation for Project Managers

Use utf8proj status for daily standups:

utf8proj status project.proj                 # Text dashboard
utf8proj status project.proj --format json   # JSON for automation
utf8proj status project.proj --as-of DATE    # Historical view

The status command provides:

  1. Daily standup answer: "Where are we?" in 2 seconds
  2. Progress metrics: Overall %, variance, earned value (SPI)
  3. Task breakdown: Complete, in-progress, not-started, behind counts
  4. Critical path: Number of tasks and days remaining

For Excel reports with status dashboard, use:

utf8proj gantt project.proj -o report.xlsx -f xlsx --include-status

Implementation Dependencies

utf8proj status ✓ DONE (RFC-0019)
    ↓
utf8proj progress (needs status to show result)
    ↓
Extended TaskStatus (enhances progress command)
    ↓
utf8proj forecast (combines status + baseline)
    ↓
utf8proj playback (needs multiple baselines)