it depends, the N+1 option is safe if you can do it..oversubscribe is an option, but as you say this could be bad for performance: you should be careful that the MPI is not using any CPU when idling (depends on the MPI for example openmpi has --mca mpi_yield_when_idle 1) then it should be ok. |
Beta Was this translation helpful? Give feedback.
0 replies
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
Uh oh!
There was an error while loading. Please reload this page.
Uh oh!
There was an error while loading. Please reload this page.
-
If I want to run a code (in my case POP from OMUSE) on N cores (number_of_workers), say 128, it seems like I need to request N+1, so 129, tasks (in slurm), because AMUSE will call MPI.Spawn 128 times, but the original process already used 1 task, so that makes the total 129.
What's the proper way to solve this? Is it really not possible to reuse the original process for a worker?