WormFS Overall Implementation Plan - Iterative Delivery Approach

Overview

This plan outlines the recommended implementation order for WormFS components, prioritizing iterative delivery of a working end-to-end system. The approach focuses on building a minimal viable path through the system first, then adding complexity and robustness in subsequent phases.

Implementation Phases

Phase 1: Minimal Data Path (Weeks 1-3)

Goal: Store and retrieve a single file without consensus or distribution

  1. MetadataStore (minimal)

    • Basic SQLite schema
    • File and stripe CRUD operations
    • No transactions or snapshots yet
  2. FileStore (minimal)

    • Simple chunk storage to local disk
    • Basic erasure coding (Reed-Solomon)
    • Single node operation only
    • No 2PC or staging yet
  3. FileSystemService (minimal)

    • Basic FUSE operations (create, read, write, stat)
    • Direct integration with MetadataStore and FileStore
    • No locking or concurrent access yet
  4. StorageNode (minimal)

    • Wire up the three components
    • Basic configuration loading
    • Simple main() entry point

Milestone: Can mount filesystem and create/read/write files on a single node


Phase 2: Add Consensus Layer (Weeks 4-6)

Goal: Metadata consistency across multiple nodes

  1. StorageNetwork

    • libp2p setup for node discovery
    • Basic peer-to-peer communication
    • RPC foundation for Raft
  2. TransactionLogStore

    • Raft log persistence with redb
    • Basic append and read operations
  3. StorageRaftMember

    • OpenRaft integration
    • Leader election
    • Log replication
    • Metadata operations through consensus
  4. Update MetadataStore

    • Add transaction support
    • Integrate with Raft state machine
    • Add prepare/commit/abort operations

Milestone: Multiple nodes maintain consistent metadata through Raft


Phase 3: Distributed Storage (Weeks 7-9)

Goal: Distribute chunks across nodes

  1. StorageEndpoint

    • gRPC server for client connections
    • Node-to-node chunk transfer APIs
    • Basic authentication
  2. Update FileStore

    • Implement 2PC for chunk operations
    • Add chunk staging/activation
    • Remote chunk fetching
    • Chunk placement logic
  3. Update FileSystemService

    • Add file locking
    • Stripe coordination across nodes
    • Read-modify-write for partial stripes

Milestone: Files are erasure-coded and distributed across cluster


Phase 4: Robustness & Recovery (Weeks 10-11)

Goal: Handle failures gracefully

  1. SnapshotStore

    • Metadata snapshot creation
    • Snapshot transfer between nodes
    • Log compaction support
  2. StorageWatchdog

    • Chunk verification (shallow & deep)
    • Missing chunk detection
    • Basic repair coordination
    • Orphan cleanup
  3. Update StorageRaftMember

    • Snapshot coordination
    • Membership changes (add/remove nodes)
    • Transaction recovery

Milestone: System recovers from node failures and maintains data integrity


Phase 5: Observability & Testing (Week 12)

Goal: Production readiness

  1. MetricService

    • Prometheus metrics
    • Health endpoints
    • Performance monitoring
  2. WormValidator

    • End-to-end test scenarios
    • Chaos testing
    • Performance benchmarks
  3. StorageNode (complete)

    • Graceful shutdown
    • Component lifecycle management
    • Production configuration

Milestone: System is observable, testable, and production-ready


Key Implementation Principles

  1. Stub Early, Implement Later: Use stub implementations for complex features initially
  2. Single Node First: Get everything working on one node before adding distribution
  3. Metadata Before Data: Focus on metadata consistency before chunk distribution
  4. Read Path Before Write Path: Implement read operations before complex write paths
  5. Manual Before Automatic: Manual recovery before automatic healing

Alternative Paths to Consider

If prioritizing early user feedback:

  • Move StorageEndpoint earlier (after Phase 1) for basic client API
  • Implement a simple CLI client alongside Phase 1

If prioritizing data safety:

  • Move SnapshotStore to Phase 2 (right after Raft)
  • Implement basic StorageWatchdog verification in Phase 3

If prioritizing performance testing:

  • Implement basic MetricService in Phase 2
  • Add simple benchmarking throughout each phase

Minimizing Throwaway Work

This plan minimizes throwaway work by:

  • Building on each component incrementally
  • Using interfaces/traits defined in scaffolding
  • Adding complexity gradually to working systems
  • Keeping test coverage from day one

Success Metrics per Phase

Phase Success Criteria
1 Single-node file operations work via FUSE mount
2 3-node cluster maintains consistent metadata
3 Files distribute across nodes with erasure coding
4 System recovers from single node failure
5 95% test coverage, <1s latency for small files

Risk Mitigation

Technical Risks:

  • FUSE complexity: Start with read-only operations if write proves difficult
  • Erasure coding performance: Begin with replication, add erasure coding later
  • Raft integration: Use raft-rs example code as reference implementation

Schedule Risks:

  • 12-week timeline aggressive: Each phase has "must have" vs "nice to have" features
  • Testing may reveal issues: Budget 20% time for bug fixes and refactoring
  • Integration complexity: Maintain integration tests from Phase 1

Next Steps

  1. Create detailed task breakdown for Phase 1
  2. Set up development environment with test infrastructure
  3. Implement MetadataStore SQLite schema
  4. Begin weekly progress reviews

Notes

  • This plan assumes full-time development effort
  • Actual timeline may vary based on complexity discoveries
  • Each phase should produce working software that can be demoed
  • Documentation should be maintained throughout, not just at the end