Prior to your building surveyor applying for your build permits with the local council the following checks must be verified:

  • Client-owner information and contract signed
  • Legal documents and certification checks
  • Government property information and overlays
  • Local council residential requirements
  • Civil works foundation and footing for slab/floor checks
  • Architectural design schematic checks

Below are lists of checks which your building surveyor will verify with the owner, builder and designer.

Client-owner information:

  • Owner details: name, email, phone, postal, profession, dependents.
  • Property history & future legacy
  • Building purpose and occupant use
  • Expectations: cost and length of build?
  • Owner/builder insurance or nominated builder insurance
  • Names and contact details of build team
  • Permission to engage with builders and designers autonomously
  • Signature to retain client/build information for 10 years

Legal documents and certifications:

  • Overlays (bushfire, heritage, indigenous, etc)
  • Site plans
  • Geotechnical report
  • Soil certification report with address nominated
  • BAL assessment report
  • Town planning permit
  • Residential witholding tax
  • Building surveyor application form
  • Footing / slab design
  • Structural computations
  • Certificate of compliance
  • Energy report
  • Land ownership title (contract of sale if not in owners name)
  • Transfer of land (verifying ownership)
  • Cost of works certificate
  • Owner-builder permit (for +$16k works)
  • Registered builder warranty insurance, including: date span, cost of works matches,
  • Evidence of build funds
  • Payment of surveyor %1 of total build cost
  • Copy of building contract (owner name same as land deed)
  • Build over easement consent (water authority or council)
  • Protection work forms 7 & 8
  • Request for partial compliance / excemption to building regulations letter / performance solution
  • Building appeals board approvals
  • Legal point of discharge (stormwater)
  • Easement locations (zoning)
  • Covenants
  • 173 agreements (pre-contract developer requirements)
  • Building envelope

Government property & overlay information:

  • Sitting maters (overlays, covenents, part 5 Build Regs VBA)
  • Planning permit endorsed plans
  • Planning permit conditions
  • Bushfire attack level
  • Septic sewer approval
  • Infrastructure levy (VBA practice note 54)
  • Developers approval

Residential (local council) preliminary checks:

  • building height / stories
  • street setback
  • siting coverage
  • side and rear setback
  • wall and boundaries
  • front fence height
  • fence on boundaries
  • fence within street intersection
  • permeability
  • parking
  • existing windows
  • existing north facing windows
  • daylight to habitable rooms
  • overshadowing
  • overlooking
  • private open space
  • garden space required
  • verandahs / pagodas / etc

Civil works foundation & footing for slab/floor preliminary checks:

  • soil classification
  • slab dimensions matches floor plans
  • dpeth as per soil report
  • root barriers
  • steel rebar reinforcement
  • re-entry bars / fixings for footings
  • penetration locations
  • vapour barrier

Architectural schematic prelimary checks:

  • correct address / geo marker
  • site plan / floor plan
  • all existing buildings show on site
  • elevations
  • allotment dimensions
  • boundary setbacks
  • FRL for boundary properties
  • sectional drawings
  • plans to scale
  • azimuth
  • distance to nearest street corner
  • adjoining neighbors setback
  • timber schedule
  • window schedule
  • area for each room
  • pier schematics
  • site survey plan
  • energy (6 star) plans correspond
  • wind category nominated
  • site drainage shown
  • insulation details
  • septic and rain drain
  • retaining wall design
  • plumbing joints for reactive soil sites
  • beam sizes
  • lintel sizes
  • bracing shown
  • roof pitch nominated
  • storm water downpipes shown
  • carport / garage / shed / construction material storage?
  • stair rise/going dimensions, e.g. Rise=115-190 / Going=240-355
  • garage step down
  • required sanitary facilities
  • ceiling height: 2.4m(min) / Kitchen 2.1m(min)
  • smoke detectors
  • removal hinges for WC
  • mechanical ducted ventilation (WC, laundry, bathroom)
  • electrical lighting with wattage
  • waterproofing in wet areas
  • fire place details
  • chimney height
  • party wall details
  • acoustic seperation details
  • cladding details & specs (foam, hebel, steel cement sheet, etc)
  • pavement fall
  • subfloor ventilation