Milestones

List view

  • No due date
    1/1 issues closed
  • No due date
    2/2 issues closed
  • What's in: - Resuming Requests - Listing Of Status For Requests - Single Round Trip Flow For Pull Requests - Integration in go-filecoin codebase What's out: - Single round trip flow for Push? - Additional speed optimization and testing

    Overdue by 5 year(s)
    Due by January 12, 2020
    9/9 issues closed
  • This is an initial implementation of the data transfer spec. Covered: - Round trip push / pull using data transfer protocol, scheduling, and Graphsync - 2 round trip version for pull - all prerequisite work - Integration In Lotus Codebase Not covered: - resuming requests - single round trip pull flow - listing in progress data transfers

    Overdue by 6 year(s)
    Due by December 11, 2019
    26/26 issues closed