Attachment Dates appear to include the date of migration rather than actual date of upload #1700
-
When enabling AttachmentMigration and ReplayRevisions in the WorkItemMigrationContext processor, the attachments come over on the migrated work item. However, the Date Attached reflects the date of the migration instead of matching the Date Attached on the original item. Is this something that can be fixed? |
Beta Was this translation helpful? Give feedback.
Replies: 2 comments
-
I don't believe there is any way to override the date on the attachment. |
Beta Was this translation helpful? Give feedback.
-
Thank you for confirming! I will let my Azure Boards teams know to plan for this behavior when migrating. |
Beta Was this translation helpful? Give feedback.
I don't believe there is any way to override the date on the attachment.