Lines changed: 4 additions & 4 deletions
Original file line numberDiff line numberDiff line change
@@ -9,9 +9,9 @@
99
[options="header"]
1010
|===
1111
|Version |General availability |End of life
12-
|4.11 |Aug 10, 2022 |Jun 10, 2023
13-
|4.10 |Mar 10, 2022 |Jan 10, 2023
14-
|4.9 |Oct 18, 2021 |Sep 28, 2022
15-
|4.8 |Jul 27, 2021 |Aug 31, 2022
12+
|4.11 |Aug 10, 2022 |Oct 10, 2023
13+
|4.10 |Mar 10, 2022 |May 10, 2023
14+
|4.9 |Oct 18, 2021 |Dec 18, 2022
15+
|4.8 |Jul 27, 2021 |Sep 27, 2022
1616

1717
|===

modules/life-cycle-minor-versions.adoc

Lines changed: 7 additions & 7 deletions
Original file line numberDiff line numberDiff line change
@@ -6,17 +6,17 @@
66
= Minor versions (x.Y.z)
77

88
Starting with the 4.8 OpenShift Container Platform minor version, Red Hat supports all minor
9-
versions within a 9 month period following general availability of the given minor version. Patch
10-
versions do not affect the 9 month supportability period.
9+
versions within a 14 month period following general availability of the given minor version. Patch
10+
versions are not affected by the 14 month supportability period.
1111

12-
Customers are notified 60, 30, and 15 days prior to the end of the 9 month period. Clusters must be upgraded to
13-
a supported minor version prior to the end of the 9 month period, or the cluster will enter
12+
Customers are notified 60, 30, and 15 days prior to the end of the 14 month period. Clusters must be upgraded to
13+
a supported minor version prior to the end of the 14 month period, or the cluster will enter
1414
a "Limited Support" status.
1515

1616
.Example
1717
. A customer's cluster is currently running on 4.8.14. The 4.8 minor version became generally
1818
available on July 27, 2021.
19-
. On Feb 26, March 28, and April 12, 2022, the customer is notified that their cluster will enter "Limited Support" status
20-
on April 27, 2022 if the cluster has not already been upgraded to a supported minor version.
21-
. The cluster must be upgraded to 4.9 or later by April 27, 2022.
19+
. On July 29, August 28, and September 12, 2022, the customer is notified that their cluster will enter "Limited Support" status
20+
on September 27, 2022 if the cluster has not already been upgraded to a supported minor version.
21+
. The cluster must be upgraded to 4.9 or later by September 27, 2022.
2222
. If the upgrade has not been performed, the cluster will be flagged as being in a "Limited Support" status.

0 commit comments