Hi

I had a discussion with @gilles-duboscq and others about this.

The current approach would be to create a ticket with details of the PR you want a backport for, mention @gilles-duboscq and @ezzarghili in your issue to bring attention to it if release code freeze date is near (~within 15 days of the deadline), we can still take in backports exceptionally after if it is critical enough and release date will not be compromised.

Backports will require the component lead approval.

The more critical a bug fix is the better chance it will get approved, the small bug fixes that have low chance of breaking something can also be approved as long as they are filed long before the code freeze date.