| Well diameter | 9⅝ inches | Next standard size up from 7", implied by announcement of "increasing casing diameter" |
36
36
| Flow Rate per Production Well | 107 kg/s | Maximum flow rate achieved at Cape Station per https://www.businesswire.com/news/home/20240910997008/en/Fervo-Energys-Record-Breaking-Production-Results-Showcase-Rapid-Scale-Up-of-Enhanced-Geothermal. The announced increased casing diameter implies higher flow rates. |
37
-
| Number of doublets |54| Estimate based on extrapolation from [Project Red](https://gtp.scientificwebservices.com/geophires/?geophires-example-id=Fervo_Norbeck_Latimer_2023) and [Fervo_Project_Cape-3](https://gtp.scientificwebservices.com/geophires/?geophires-example-id=Fervo_Project_Cape-3)|
37
+
| Number of doublets |59| Estimate based on extrapolation from previous case studies including [Project Red](https://gtp.scientificwebservices.com/geophires/?geophires-example-id=Fervo_Norbeck_Latimer_2023) and [Fervo_Project_Cape-3](https://gtp.scientificwebservices.com/geophires/?geophires-example-id=Fervo_Project_Cape-3)|
38
38
| Fracture Separation | 18 m | Per https://eartharxiv.org/repository/view/7665/, lateral length is 4700 ft = 1432 m. Dividing 1432 by 80 = ~18 m fracture spacing. |
39
39
| Reservoir Volume | 5,801,599,999 m³ | Extrapolation based on a resulting heat extraction profile that is plausible and compatible with required electricity production. |
40
40
| Water Loss Rate | 15% | Water loss rate estimated to be between 10 and 20% |
41
-
| Maximum Drawdown | 0.009| Tuned to keep minimum net electricity generation ≥ 500 MWe and thermal breakthrough requiring redrilling occurring every 5–10 years |
42
-
| Reservoir Impedance | 0.001 GPa.s/m³ | Same as 400 MWe case study (Fervo_Project_Cape-3) |
41
+
| Maximum Drawdown | 0.017| Tuned to keep minimum net electricity generation ≥ 500 MWe and thermal breakthrough requiring redrilling occurring every 5–10 years |
| Inflation Rate | 2.3% | US inflation rate as of April 2025 |
44
44
| PPA Price | Starting at 9.5 cents/kWh, escalating to 10 cents/kWh by project year 11 | Upper end of ranges given in https://atb.nrel.gov/electricity/2024/geothermal. Both PPAs 'firm for 10 years at less than $100/MWh' estimate given in a podcast. |
45
45
| Well Drilling Cost Correlation & Adjustment Factor | Vertical large baseline correlation + adjustment factor = 0.84 to align with Fervo claimed drilling costs of <$4M/well | Akindipe, D. and Witter. E. 2025. "2025 Geothermal Drilling Cost Curves Update". https://pangea.stanford.edu/ERE/db/GeoConf/papers/SGW/2025/Akindipe.pdf?t=1740084555; Latimer, T. (2025, February 12). Catching up with enhanced geothermal (D. Roberts, Interviewer). https://www.volts.wtf/p/catching-up-with-enhanced-geothermal.|
@@ -58,14 +58,14 @@ in source code for the full set of inputs.
58
58
59
59
| Metric | Result Value | Reference Value(s) | Reference Source |
| Project capital costs |~$4200/kW (based on maximum total electricity generation) | $4500/kW, $3000–$6000/kW |https://www.nature.com/articles/s44359-024-00019-9; Latimer, T. (2025, February 12). Catching up with enhanced geothermal (D. Roberts, Interviewer). https://www.volts.wtf/p/catching-up-with-enhanced-geothermal.|
63
-
| Maximum Total Electricity Generation |563 MW || Actual maximum total generation may be bounded or constrained by modular power plant design not modeled in this case study. For example, a modular design with 50MW units may constrain maximum total generation to 550 MW. |
64
-
| Minimum Net Electricity Generation |505 MW | 500 MW |https://fervoenergy.com/fervo-energy-announces-31-mw-power-purchase-agreement-with-shell-energy/. The 500 MW PPA is interpreted to mean that Cape Station's net electricity generation must never fall below 500 MWe. |
65
-
| Average Production Temperature |199.1℃ | 204℃, 190.6–198.6℃ (optimal plant operating range) |https://jpt.spe.org/fervo-and-forge-report-breakthrough-test-results-signaling-more-progress-for-enhanced-geothermal; https://eartharxiv.org/repository/view/7665/.|
63
+
| Maximum Total Electricity Generation |615 MW || Actual maximum total generation may be bounded or constrained by modular power plant design not modeled in this case study. For example, a modular design with 50MW units may constrain maximum total generation to 600 MW. |
64
+
| Minimum Net Electricity Generation |500 MW | 500 MW |https://fervoenergy.com/fervo-energy-announces-31-mw-power-purchase-agreement-with-shell-energy/. The 500 MW PPA is interpreted to mean that Cape Station's net electricity generation must never fall below 500 MWe. |
65
+
| Average Production Temperature |198.9℃ | 204℃, 190.6–198.6℃ (optimal plant operating range) |https://jpt.spe.org/fervo-and-forge-report-breakthrough-test-results-signaling-more-progress-for-enhanced-geothermal; https://eartharxiv.org/repository/view/7665/.|
66
66
| Well Drilling and Completion Cost Correlation | $3.96M/well | $<4M/well | Latimer, T. (2025, February 12). Catching up with enhanced geothermal (D. Roberts, Interviewer). https://www.volts.wtf/p/catching-up-with-enhanced-geothermal|