Set Field Gathering System Capital Cost Adjustment Factor
1 parent d819fb6 commit 2ca8f92

File tree

3 files changed

+75
-71
lines changed

3 files changed

+75
-71
lines changed

docs/Fervo_Project_Cape-4.md

Lines changed: 3 additions & 3 deletions
Original file line numberDiff line numberDiff line change
@@ -58,14 +58,14 @@ in source code for the full set of inputs.
5858

5959
| Metric | Result Value | Reference Value(s) | Reference Source |
6060
|-----------------------------------------------|-----------------------------------------------------------|----------------------------------------------------|-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------|
61-
| LCOE | $82.7/MWh | $80/MWh | https://www.nature.com/articles/s44359-024-00019-9 |
62-
| Project capital costs | ~$4200/kW (based on maximum total electricity generation) | $4500/kW, $3000–$6000/kW | https://www.nature.com/articles/s44359-024-00019-9; Latimer, T. (2025, February 12). Catching up with enhanced geothermal (D. Roberts, Interviewer). https://www.volts.wtf/p/catching-up-with-enhanced-geothermal. |
61+
| LCOE | $81.6/MWh | $80/MWh | https://www.nature.com/articles/s44359-024-00019-9 |
62+
| Project capital costs | ~$4500/kW (based on maximum total electricity generation) | $4500/kW, $3000–$6000/kW | https://www.nature.com/articles/s44359-024-00019-9; Latimer, T. (2025, February 12). Catching up with enhanced geothermal (D. Roberts, Interviewer). https://www.volts.wtf/p/catching-up-with-enhanced-geothermal. |
6363
| Maximum Total Electricity Generation | 615 MW | | Actual maximum total generation may be bounded or constrained by modular power plant design not modeled in this case study. For example, a modular design with 50MW units may constrain maximum total generation to 600 MW. |
6464
| Minimum Net Electricity Generation | 500 MW | 500 MW | https://fervoenergy.com/fervo-energy-announces-31-mw-power-purchase-agreement-with-shell-energy/. The 500 MW PPA is interpreted to mean that Cape Station's net electricity generation must never fall below 500 MWe. |
6565
| Average Production Temperature | 198.9℃ | 204℃, 190.6–198.6℃ (optimal plant operating range) | https://jpt.spe.org/fervo-and-forge-report-breakthrough-test-results-signaling-more-progress-for-enhanced-geothermal; https://eartharxiv.org/repository/view/7665/. |
6666
| Well Drilling and Completion Cost Correlation | $3.96M/well | $<4M/well | Latimer, T. (2025, February 12). Catching up with enhanced geothermal (D. Roberts, Interviewer). https://www.volts.wtf/p/catching-up-with-enhanced-geothermal |
6767
| WACC | 8.3% | 8.3% | https://www.linkedin.com/pulse/fervo-energy-technology-day-2024-entering-geothermal-decade-matson-n4stc |
68-
| After-tax IRR | 24.83% | 15–25% | Typical levered returns for energy projects |
68+
| After-tax IRR | 25.85% | 15–25% | Typical levered returns for energy projects |
6969
| Number of times redrilling | 2 | 1–4 | Redrilling expected to be required within 5–10 years of project start |
7070

7171
See [Fervo_Project_Cape-4.out](https://github.com/softwareengineerprogrammer/GEOPHIRES/blob/main/tests/examples/Fervo_Project_Cape-4.out)