Revert lateral length back to 4700 feet to align with well cost assumption
1 parent 7c4bc8a commit 34c6534

File tree

2 files changed

+6
-6
lines changed

2 files changed

+6
-6
lines changed

tests/examples/Fervo_Project_Cape-3.out

Lines changed: 4 additions & 4 deletions
Original file line numberDiff line numberDiff line change
@@ -4,10 +4,10 @@
44

55
Simulation Metadata
66
----------------------
7-
GEOPHIRES Version: 3.6.3
8-
Simulation Date: 2024-11-12
9-
Simulation Time: 13:08
10-
Calculation Time: 0.870 sec
7+
GEOPHIRES Version: 3.6.4
8+
Simulation Date: 2024-11-13
9+
Simulation Time: 10:52
10+
Calculation Time: 0.863 sec
1111

1212
***SUMMARY OF RESULTS***
1313

tests/examples/Fervo_Project_Cape-3.txt

Lines changed: 2 additions & 2 deletions
Original file line numberDiff line numberDiff line change
@@ -43,6 +43,7 @@ Plant Lifetime, 20
4343
Power Plant Type, 2
4444
Circulation Pump Efficiency, 0.80
4545

46+
Surface Plant Capital Cost Adjustment Factor, 0.71, -- $1900/kW (peak production)
4647
Exploration Capital Cost, 30
4748
Well Drilling and Completion Capital Cost, 3.84, -- Assume cost continues to decrease from $4.8M/well (https://houston.innovationmap.com/fervo-energy-drilling-utah-project-2667300142.html)
4849
Reservoir Stimulation Capital Cost, 234, -- 78 wells @ $3M/well
@@ -63,9 +64,8 @@ Property Tax Rate, 0
6364
Time steps per year, 10
6465
Maximum Temperature, 500
6566

66-
Surface Plant Capital Cost Adjustment Factor, 0.71, -- $1900/kW (peak production)
6767
Well Geometry Configuration, 4
6868
Has Nonvertical Section, True
6969
Multilaterals Cased, True
7070
Number of Multilateral Sections, 3
71-
Nonvertical Length per Multilateral Section, 7500 feet
71+
Nonvertical Length per Multilateral Section, 4700 feet