docs/Fervo_Project_Cape-4.md

Lines changed: 11 additions & 11 deletions
Original file line numberDiff line numberDiff line change
@@ -12,8 +12,8 @@ comparison of results with reference values.
1212
| Parameter | Input Value(s) | Source |
1313
|-----------------------------------------------------------|--------------------------------------------------------------------------|---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------|
1414
| Well diameter | 9⅝ inches | Next standard size up from 7", implied by announcement of "increasing casing diameter" |
15-
| Flow Rate per Production Well | 115 kg/s | Project Red stable and peak flows: 93–120 kg/s. Estimate on higher end of range chosen due to increased casing diameter implying higher flow rates. |
16-
| Number of doublets | 50 | Estimate based on extrapolation from Project Red |
15+
| Flow Rate per Production Well | 107 kg/s | Maximum flow rate achieved at Cape Station per https://www.businesswire.com/news/home/20240910997008/en/Fervo-Energys-Record-Breaking-Production-Results-Showcase-Rapid-Scale-Up-of-Enhanced-Geothermal. The announced increased casing diameter implies higher flow rates. |
16+
| Number of doublets | 54 | Estimate based on extrapolation from Project Red and Fervo_Project_Cape-3 |
1717
| Reservoir size & geometry | 149 rectangular 1400m×1400m fractures; 30m fracture separation | Actual number and size of fractures not known; inputs chosen to create reservoir volume that is compatible with required heat extraction profile. |
1818
| Water Loss Rate | 15% | Water loss rate estimated to be between 10 and 20% |
1919
| Maximum Drawdown | 0.009 | Tuned to keep minimum net electricity generation ≥ 500 MWe and number of times redrilling = 1 |
@@ -30,12 +30,12 @@ comparison of results with reference values.
3030

3131
## Results
3232

33-
| Metric | Result Value | Reference Value | Reference Source |
34-
|-----------------------------------------------|----------------------------------------------------------------------------|-----------------|-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------|
35-
| LCOE | $74.1/MWh | $80/MWh | https://www.nature.com/articles/s44359-024-00019-9 |
36-
| Plant capital costs | $4581/kW (based on maximum net total electricity generation of 523.68 MW) | $4500/kW | https://www.nature.com/articles/s44359-024-00019-9 |
37-
| Minimum Net Electricity Generation | 502.72 MW | 500 MW | https://fervoenergy.com/fervo-energy-announces-31-mw-power-purchase-agreement-with-shell-energy/. The 500 MW PPA is interpreted to mean that Cape Station's net electricity generation must never fall below 500 MWe. |
38-
| Well Drilling and Completion Cost Correlation | $4.72M/well | $4.8M/well | https://houston.innovationmap.com/fervo-energy-drilling-utah-project-2667300142.html |
39-
| WACC | 8.3% | 8.3% | https://www.linkedin.com/pulse/fervo-energy-technology-day-2024-entering-geothermal-decade-matson-n4stc |
40-
| After-tax IRR | 18.28% | 15–25% | Typical levered returns for energy projects |
41-
| Number of times redrilling | 1 | 1–2 | Redrilling expected to be required within 5–10 years of project start |
33+
| Metric | Result Value | Reference Value | Reference Source |
34+
|-----------------------------------------------|-----------------------------------------------------------------------|-----------------|-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------|
35+
| LCOE | $75.3/MWh | $80/MWh | https://www.nature.com/articles/s44359-024-00019-9 |
36+
| Plant capital costs | $4375/kW (based on maximum total electricity generation of 562.54 MW) | $4500/kW | https://www.nature.com/articles/s44359-024-00019-9 |
37+
| Minimum Net Electricity Generation | 504.64 MW | 500 MW | https://fervoenergy.com/fervo-energy-announces-31-mw-power-purchase-agreement-with-shell-energy/. The 500 MW PPA is interpreted to mean that Cape Station's net electricity generation must never fall below 500 MWe. |
38+
| Well Drilling and Completion Cost Correlation | $4.72M/well | $4.8M/well | https://houston.innovationmap.com/fervo-energy-drilling-utah-project-2667300142.html |
39+
| WACC | 8.3% | 8.3% | https://www.linkedin.com/pulse/fervo-energy-technology-day-2024-entering-geothermal-decade-matson-n4stc |
40+
| After-tax IRR | 17.73% | 15–25% | Typical levered returns for energy projects |
41+
| Number of times redrilling | 1 | 1–2 | Redrilling expected to be required within 5–10 years of project start |