# Case Study: Fervo Project Cape 3: Extrapolation from Fervo results pre-published 2024-09-10 at
2
2
# https://eartharxiv.org/repository/view/7665/ to 400MWe capacity.
3
-
# Norbeck J., Gradl C., and Latimer T. 2024.
3
+
# Norbeck J., -- Gradl C., and Latimer T. 2024.
4
4
# "Deployment of Enhanced Geothermal System technology leads to rapid cost reductions and performance improvements."
5
5
# https://doi.org/10.31223/X5VH8C
6
-
7
-
8
6
Reservoir Model, 1
9
7
Reservoir Volume Option, 1
10
8
Reservoir Density, 2800
@@ -13,16 +11,13 @@ Reservoir Heat Capacity, 790
13
11
Reservoir Thermal Conductivity, 3.05
14
12
Reservoir Porosity, 0.0118
15
13
Reservoir Impedance, 0.001
16
-
17
14
Number of Fractures, 149
18
15
Fracture Shape, 4
19
16
Fracture Height, 2000
20
17
Fracture Width, 10000
21
18
Fracture Separation, 30
22
-
23
19
Number of Segments, 1
24
20
Gradient 1, 74, -- temperature at 8500 ft: 200 degC (https://pangea.stanford.edu/ERE/db/GeoConf/papers/SGW/2024/Fercho.pdf); 228.89 degC @ 9824 ft (https://doi.org/10.31223/X5VH8C)
25
-
26
21
Number of Injection Wells, 39
27
22
Number of Production Wells, 39
28
23
Production Flow Rate per Well, 120, -- peak flow reported in paper
@@ -40,13 +35,12 @@ Maximum Drawdown, 1
40
35
Ambient Temperature, 10 degC
41
36
Surface Temperature, 10 degC
42
37
End-Use Option, 1
43
-
Plant Lifetime, 15
38
+
Plant Lifetime, 20
44
39
Power Plant Type, 2
45
40
Circulation Pump Efficiency, 0.80
46
-
47
-
Exploration Capital Cost, 0
48
-
Well Drilling and Completion Capital Cost, 4, -- Assume cost continues to decrease from 4.8 (https://houston.innovationmap.com/fervo-energy-drilling-utah-project-2667300142.html)
49
-
Reservoir Stimulation Capital Cost, 78, -- $1M/well estimated
41
+
Exploration Capital Cost, 30
42
+
Well Drilling and Completion Capital Cost, 5.84, -- $3.84M/well + $2M/well additional stimulation cost
43
+
Reservoir Stimulation Capital Cost, 78, -- $3M/well - $1M as stimulation + $2M represented in well drilling cost
50
44
Economic Model, 3
51
45
Starting Electricity Sale Price, 0.15
52
46
Ending Electricity Sale Price, 1.00
@@ -58,15 +52,14 @@ Gross Revenue Tax Rate, 0
58
52
Inflated Bond Interest Rate, .05
59
53
Inflated Equity Interest Rate, .08
60
54
Inflation Rate, .02
61
-
Investment Tax Credit Rate, 0
55
+
Investment Tax Credit Rate, .3
62
56
Inflation Rate During Construction, 0.05
63
57
Property Tax Rate, 0
64
58
Time steps per year, 10
65
59
Maximum Temperature, 500
66
-
Surface Plant Capital Cost Adjustment Factor, 0.78, -- pad drilling reduces surface CAPEX by 22% https://www.resfrac.com/blog/digesting-the-bonkers-incredible-off-the-charts-spectacular-results-from-the-fervo-and-forge-enhanced-geothermal-projects