JIRA to TaskJuggler Convertor

Tool for converting a set of JIRA tasks to TaskJuggler (TJ3) syntax, with support for hierarchical task structures including Epics, Stories, and Sub-tasks.

Goal

When using JIRA to track your project, and tasks/issues are estimated using the time-tracking plugin, this python module can convert the JIRA tasks to a gantt chart using the TaskJuggler tool.

The tool supports both flat task lists and hierarchical task structures. With the hierarchical mode enabled, Epics become parent tasks containing their child Stories and Sub-tasks, creating properly nested TaskJuggler task structures with automatic effort rollup from children to parents.

Installation

Installation from PyPI:

pip install mlx.jira-juggler

Usage

See help from python module:

jira-juggler -h

By default, the following endpoint for the JIRA API is used: https://melexis.atlassian.net. The script will ask you to input your email address (or username) and API token (or password). These three variables can be configured by setting them in a .env file. This .env file shall be located in the directory where pip has installed the package. You can find an example configuration in .env.example. JIRA Cloud requires the combination of email address and API token, while JIRA Server might accept a username and password.

Basic Usage:

jira-juggler -q "project = MYPROJECT" -o output.tjp

Hierarchical Epic Support:

To enable hierarchical task structures with Epics, Stories, and Sub-tasks, use the -E or --enable-epics flag:

jira-juggler -q "project = MYPROJECT" -E -o hierarchical_output.tjp

This will create nested TaskJuggler tasks where:

  • Epics become parent tasks containing their child Stories
  • Stories become parent tasks containing their child Sub-tasks
  • Effort is automatically rolled up from children to parents
  • Proper indentation is used for nested task structures

Example Hierarchical Output:

task EPIC_123 "User Management" {
    Jira "EPIC-123"
    allocate product_owner
    effort 5.0d

    task STORY_456 "User Authentication" {
        Jira "STORY-456"
        allocate backend_dev
        effort 3.0d

        task SUB_789 "Login API" {
            Jira "SUB-789"
            allocate backend_dev
            effort 1.0d
        }
    }
}

Note

To include resolved and unresolved tasks while excluding invalid tasks, you can add the following logic to the value for the --query argument: (resolution != Invalid OR resolution = Unresolved).

Warning

The generated tj3-file, can at the moment not be parsed by TaskJuggler directly. Only the tasks are exported to the tj3-file. The list of tasks needs to be embedded in a complete tj3-file. See the TaskJuggler website for more details.

Note

Unresolved tasks with logged time, i.e. time spent, will have their 'start' property set to the set current date and time minus the logged time, calculated with 8 hours per workday and a default of 5 allocated workdays per week with the day(s) off ending on Sunday. The latter number can be changed.

Note

Epic and Hierarchy Detection: The tool automatically detects hierarchical relationships through:

  • Epic relationships: Stories/Tasks linked to Epics via epic, epiclink, or custom fields like customfield_10014
  • Parent-child relationships: Sub-tasks linked to their parent Stories/Tasks via the parent field
  • Issue types: Automatic detection of Epic and Sub-task issue types

Only tasks included in your query results will be part of the hierarchy. Child tasks without their parents in the query results will appear as standalone top-level tasks.

Command-line Options

Key command-line options include:

  • -q, --query: Required. JQL query to fetch issues from JIRA
  • -o, --output: Output .tjp file (default: jira_export.tjp)
  • -E, --enable-epics: NEW. Enable hierarchical Epic/Story/Sub-task support
  • -D, --depend-on-preceding: Make tasks depend on preceding task with same assignee
  • -s, --sort-on-sprint: Sort tasks by sprint field (e.g., customfield_10851)
  • -w, --weeklymax: Workdays per week for time calculations (default: 5.0)
  • -L, --links: Specify issue link types for dependencies
  • -l, --loglevel: Logging level (default: warning)

Run jira-juggler -h for complete help.

Comparison Example:

Without -E (flat output):

task EPIC_123 "User Management" { ... }
task STORY_456 "User Authentication" { ... }
task SUB_789 "Login API" { ... }

With -E (hierarchical output):

task EPIC_123 "User Management" {
    task STORY_456 "User Authentication" {
        task SUB_789 "Login API" { ... }
    }
}

Limitations

  • When two tasks end on the same date and time, TaskJuggler won't necessarily preserve the order in which the tasks appear in jira-juggler's output.
  • Hierarchical mode: Epic hierarchy is only enabled with the -E flag. By default, all tasks are output as a flat list to maintain backward compatibility.
  • Effort rollup: When using hierarchical mode, parent task efforts are automatically calculated from their children. Manual effort estimates on parent tasks (Epics/Stories with children) may be overridden by the rollup calculation.