Skip to content

Commit 46e49ae

Browse files
Switch to RES_VOL_FRAC_SEP for realistic fracture size/count
1 parent 4e19462 commit 46e49ae

File tree

3 files changed

+152
-154
lines changed

3 files changed

+152
-154
lines changed

docs/Fervo_Project_Cape-4.md

Lines changed: 10 additions & 10 deletions
Original file line numberDiff line numberDiff line change
@@ -14,7 +14,7 @@ comparison of results with reference values.
1414
| Well diameter | 9⅝ inches | Next standard size up from 7", implied by announcement of "increasing casing diameter" |
1515
| Flow Rate per Production Well | 107 kg/s | Maximum flow rate achieved at Cape Station per https://www.businesswire.com/news/home/20240910997008/en/Fervo-Energys-Record-Breaking-Production-Results-Showcase-Rapid-Scale-Up-of-Enhanced-Geothermal. The announced increased casing diameter implies higher flow rates. |
1616
| Number of doublets | 54 | Estimate based on extrapolation from Project Red and Fervo_Project_Cape-3 |
17-
| Reservoir size & geometry | 149 rectangular 1400m×1400m fractures; 30m fracture separation | Actual number and size of fractures not known; inputs chosen to create reservoir volume that is compatible with required heat extraction profile. |
17+
| Reservoir size & geometry | Reservoir Volume = 5801599999 m**3, Fracture Separation = 10m | Extrapolation to create case study heat extraction profile. Actual number and size of fractures not known. |
1818
| Water Loss Rate | 15% | Water loss rate estimated to be between 10 and 20% |
1919
| Maximum Drawdown | 0.009 | Tuned to keep minimum net electricity generation ≥ 500 MWe and number of times redrilling = 1 |
2020
| Reservoir Impedance | 0.001 GPa.s/m³ | |
@@ -30,12 +30,12 @@ comparison of results with reference values.
3030

3131
## Results
3232

33-
| Metric | Result Value | Reference Value | Reference Source |
34-
|-----------------------------------------------|-----------------------------------------------------------------------|-----------------|-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------|
35-
| LCOE | $75.3/MWh | $80/MWh | https://www.nature.com/articles/s44359-024-00019-9 |
36-
| Plant capital costs | $4375/kW (based on maximum total electricity generation of 562.54 MW) | $4500/kW | https://www.nature.com/articles/s44359-024-00019-9 |
37-
| Minimum Net Electricity Generation | 504.64 MW | 500 MW | https://fervoenergy.com/fervo-energy-announces-31-mw-power-purchase-agreement-with-shell-energy/. The 500 MW PPA is interpreted to mean that Cape Station's net electricity generation must never fall below 500 MWe. |
38-
| Well Drilling and Completion Cost Correlation | $4.72M/well | $4.8M/well | https://houston.innovationmap.com/fervo-energy-drilling-utah-project-2667300142.html |
39-
| WACC | 8.3% | 8.3% | https://www.linkedin.com/pulse/fervo-energy-technology-day-2024-entering-geothermal-decade-matson-n4stc |
40-
| After-tax IRR | 17.73% | 15–25% | Typical levered returns for energy projects |
41-
| Number of times redrilling | 1 | 1–2 | Redrilling expected to be required within 5–10 years of project start |
33+
| Metric | Result Value | Reference Value | Reference Source |
34+
|-----------------------------------------------|----------------------------------------------------------|-----------------|-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------|
35+
| LCOE | $75.1/MWh | $80/MWh | https://www.nature.com/articles/s44359-024-00019-9 |
36+
| Plant capital costs | $4372/kW (based on maximum total electricity generation) | $4500/kW | https://www.nature.com/articles/s44359-024-00019-9 |
37+
| Minimum Net Electricity Generation | 504.82 MW | 500 MW | https://fervoenergy.com/fervo-energy-announces-31-mw-power-purchase-agreement-with-shell-energy/. The 500 MW PPA is interpreted to mean that Cape Station's net electricity generation must never fall below 500 MWe. |
38+
| Well Drilling and Completion Cost Correlation | $4.72M/well | $4.8M/well | https://houston.innovationmap.com/fervo-energy-drilling-utah-project-2667300142.html |
39+
| WACC | 8.3% | 8.3% | https://www.linkedin.com/pulse/fervo-energy-technology-day-2024-entering-geothermal-decade-matson-n4stc |
40+
| After-tax IRR | 17.77% | 15–25% | Typical levered returns for energy projects |
41+
| Number of times redrilling | 1 | 1–2 | Redrilling expected to be required within 5–10 years of project start |

0 commit comments

Comments
 (0)