List view
- Due by January 15, 2019•6/6 issues closed
- Due by January 1, 2019•5/6 issues closed
- Due by December 18, 2018•8/8 issues closed
- Due by December 4, 2018•7/7 issues closed
- Due by November 20, 2018•5/5 issues closed
- Due by November 6, 2018•6/9 issues closed
- Due by October 23, 2018•1/1 issues closed
- Due by June 19, 2018
1.4.1 FC issues * Docker Pull Improve: attach/detach operations *
Due by June 19, 2018Refactor API handlers & vic-machine code * reconfigure UI * configure UI * Update/Automate CI * Automated VIC UI Plugin Tests
Due by June 19, 2018•0/1 issues closedFix DBS exec issues * Docker Pull Improve Initial work * Finish Pen Test Scoping
Due by June 5, 2018•6/6 issues closed1.4.1 nightly blockers * VIC Machine Wizard Configure and Upgrade * Stabilize vic/vic-product nightlies * Automated UI Plugin Install * Expand vic-ui testing
Due by June 5, 2018•8/9 issues closedImage manifest JWS verification * NSX-T Support for Nightlies * Prototype Storage design for wolfpack * Investigation into Flannel
Due by June 5, 2018•6/7 issues closedFocus on 1.4.1 issues * Wolfpack work * NSXv Network Security Policy Support *
Due by May 22, 2018•5/5 issues closedFocus on 1.4.1 release issues, including DBS found issues * Upgrade * Pen Test Scoping * Docker Pull Improve Decomposition
Due by May 22, 2018•2/2 issues closedFocus on any 1.4.1 issues * Stabilizing vic/vic-product nightlies * Design Doc for OVA automation * Expand testing in vic-ui *
Due by May 22, 2018•8/8 issues closed- Due by October 9, 2018
p0 and ship-stoppers for 1.4, ROBO network/latency testing, initial decomposition of 1.5 work
Due by May 8, 2018•3/3 issues closedInitial work and decompose of Docker Pull improvements - Continue Project Wolfpack demo work and investigation - p1 test issues - incoming ship stoppers
Due by May 8, 2018•2/2 issues closedInitial VCH Wizard work and decomposition - incoming ship stoppers - p1 test issues - triage master
Due by May 8, 2018•10/10 issues closedAdd upgrade/configure support for folders, fix p0 and p1 issues. Triage: @rogeliosanchez
Due by April 24, 2018•16/16 issues closed1.4 P0 and P1 Tests development and 1.4 ship stoppers only, continue OKR and project wolfpack efforts.
Due by April 24, 2018•8/8 issues closedTheme: - vm-host-affinity - improve testing - incoming ship stoppers
Due by April 24, 2018•22/22 issues closed- Due by April 10, 2018•5/5 issues closed
This milestone will focus on working towards achieving the 1.4 Quality Plan anchor features, specifically focusing on planned bug fixing efforts including the security bugs. This will include p0 and p1 issues only. Work will also be continued on the Virtual Kublet. Container ops will also be assuming triage duty this sprint. Triage master: Ashok
Due by April 10, 2018•11/11 issues closedWrap-up ROBO features and test issues
Due by April 10, 2018•8/8 issues closedROBO: VCH and cVM ranked placement, license/feature check in vic-machine, inventory folder support
Due by March 27, 2018•10/10 issues closedThis milestone will focus on working towards achieving the 1.4 Quality Plan anchor features, specifically focusing on planned bug fixing efforts. This will include p0 and p1 issues only.
Due by March 27, 2018•14/14 issues closed- Due by March 27, 2018•9/9 issues closed
This milestone will focus on working towards achieving the 1.4 Quality Plan anchor features, specifically focusing on planned bug fixing efforts as well as HaaS issues. This will include p0 and p1 issues only. Additionally, project wolfpack will continue work on code refactoring and prototype 1.5(integration work with PKS). Triage master: sgairo
Due by March 13, 2018•7/7 issues closedContinue ROBO work, fill remaining cycles with p0 issues.
Due by March 13, 2018•3/3 issues closedHaaS. p0 and p1 only. VIC appliance upgrade automation.
Due by March 13, 2018•8/8 issues closedThis milestone will focus on working towards achieving the 1.4 Quality Plan anchor features, specifically focusing on escapes and planned bug fixing efforts. This will include p0 and p1 issues only. Additionally, project wolfpack will continue work on code refactoring and prototype 1.
Due by February 27, 2018•9/9 issues closedHaaS. p0 and p1 only. VIC appliance upgrade automation.
Due by February 27, 2018•6/6 issues closedStart working on ROBO issues, fill remaining available cycles with p0 issues.
Due by February 27, 2018•5/5 issues closedBreak down and design ROBO support, high-priority issues.
Due by February 13, 2018•2/2 issues closed- Due by February 13, 2018•4/4 issues closed
Finish work started at Vic week's hackathon. High priority issue. Start prototype for project wolfpack. Triage Master: @sgairo
Due by February 13, 2018•2/2 issues closedMain Theme for full sprint: High Priorities Foundation Specific themes: Start planning for alternate Linux kernels, and swap space configuration for cVM
Due by January 16, 2018•1/1 issues closedContinue to improve QA coverage for Create/Delete and Automate OVA CI tests, Start planning Reconfigure and Update work
Due by January 16, 2018•2/2 issues closedHigh priority issues, project wolfpack (multi-container VMs) and docker healthcheck (if possible).
Due by January 16, 2018•6/6 issues closedHigh priority - Assist with 1.3 blockers
Due by December 20, 2017•4/4 issues closed- Due by December 20, 2017•4/4 issues closed
Light, pre-holiday sprint. R&D kickoff for project wolfpack (multi-container VMs). Work on select high priority bugs and feature requests from customers. Stand ready to assist with 1.3 ship blockers.
Due by December 19, 2017•1/1 issues closedFix ship blockers and help out with manual testing of OVA.
Due by December 6, 2017•7/7 issues closedFix ship blockers and help out with manual testing of OVA.
Due by December 5, 2017•2/2 issues closed- Due by December 5, 2017•6/6 issues closed
high priority issues
Due by November 22, 2017•7/7 issues closed- Due by November 21, 2017•30/30 issues closed
Fix high priority bugs.
Due by November 21, 2017•9/9 issues closed